Home » 2018 School Bond Measure » School Bond Improvements » New School Building: Camas Ridge Elementary School

New School Building: Camas Ridge Elementary School

Información en español

Local voters approved the school bond measure in November 2018 to fund capital improvements at every 4J school and replace Camas Ridge Elementary School, Edison Elementary School, and North Eugene High School. The new school buildings will be high-quality facilities built for safety and security, efficiency and sustainability, modern seismic standards, and 21st-century education.

The current Camas Ridge Elementary School building was built in 1949 and is in poor condition.

The new school building is being designed now; construction will begin in 2022–23 and the new building will open in fall 2024. Students will move to a temporary school site for two years during construction of the new school.

Watch the construction progress! An aerial camera installed at the construction site shows progress with time-lapse photos that refresh every 12 minutes.

Project Updates

Camas Ridge Project News (Click to expand)

New Camas Ridge Building On the Horizon (9.14.22)
Rebuild, Reuse, Recycle: Camas Ridge (9.2.22)
Farewell Celebration for Camas Ridge Building (6.2.22)
Camas Ridge School Design Option Selected (12.17.21)
Final Camas Ridge School Design Input Sought (12.03.21)
Camas Ridge School Design Wrapping Up (10.12.21)
Final Camas Ridge School Design Open House (10.04.21)
Local Contractor Joins Camas Ridge Project Team (06.18.21)
Camas Ridge School Design Coming into Focus (05.27.21)
Camas Ridge School Design Open House (05.05.21)
Planning a New Camas Ridge: Give Feedback on Preliminary Site Plan (03.02.21)
Virtual Meeting: Camas Ridge School Design Begins (02.23.21)
Local Architect Chosen to Design New Camas Ridge (02.15.21)
Architects Sought to Design New Camas Ridge School (10.14.20)
Willard Swing School Taking Shape (04.28.20)
How, Where & When: School Rebuilding Plan Update (05.02.19)
School Board Narrows Options for School Rebuilding Plan (04.05.19)
School Rebuilding Plan Community Meeting (03.22.19)
School Design Vision & Values Workshops (02.22.19)

Design & Build

The Camas Ridge design team completed initial design development for the new Camas Ridge Elementary School in fall 2021. There is a final opportunity to give feedback on the four design options developed by the design team.

Final Camas Ridge Elementary School Design Input
Survey open through December 12 

Community Input Received

The design process for the new building began with a review of districtwide community-developed visioning, planning documents and additional reference materials. The team also assessed the property to identify opportunities and considerations for the site design of the new building.

The design process for each individual new school building includes two community open houses to provide information and seek feedback on the schematic design and design development stages. Multiple additional community meetings have been held for Camas Ridge. Due to the coronavirus pandemic, some of these events have been held online rather than in-person. The community input gathered during each phase has helped to inform the next steps of school design.

An extra early-stage online presentation also was added in March 2021 for the Camas Ridge community to review and provide input on the preliminary building siting concept. The preliminary site plan concept was then refined responsive to the community feedback received, including reducing the parking lot and relocating elements to protect an area where a large number of camas bulbs are located.

At each stage, community feedback has informed revisions and refinements of the school design. As design work is completed, community input from the final open house and feedback form will be considered for potential refinements to the near-final design.

Camas Ridge Design Development Update & Feedback – October 11 (click to expand)

On October 11, Camas Ridge families and neighbors attended an open house with the design team of Pivot Architecture to receive an update on the school’s final design, ask questions and give feedback.

The architects provided a design update about the near-final school design and showed some design renderings to showcase different views of the school design.

Community members are invited to review the design slides and share their thoughts:
Presentation Slides / Feedback Form (through Sunday, October 24)

Camas Ridge Design Feedback
www.surveymonkey.com/r/4JCamasDesign2 (Survey Closed)
Community Feedback on Design

The outdoor event was held in-person, a first in school design events since the pandemic began, with attendees wearing face masks and keeping their distance.

Camas Ridge School Schematic Design Update & Feedback – May 26 (click to expand)

Families, neighbors and community members turned out virtually on May 26 to an open house with the design team of Pivot Architecture, to get an update on school design progress, ask questions and give feedback.

The architects provided a design update incorporating design progress through schematic design, and invited questions and feedback directly to the project team to help inform the next steps of design. They started with updates and revisions—responsive to the community feedback received regarding the preliminary building siting concept in March, the project team has refined the site plan including reducing the parking lot and relocating elements to protect an area where a large number of camas bulbs are located.

Community members are invited to review the presentation and share their thoughts:
Recorded VideoPresentation Slides / Feedback Form (through Sunday, June 6)

Camas Ridge Preliminary Design Feedback
www.surveymonkey.com/r/4JCamasDesign (Survey Closed)
Community Feedback on Preliminary Design

Camas Ridge Preliminary Site Plan Presentation & Feedback – March 2 (click to expand)

Families, neighbors and community members turned out virtually on March 2 for a presentation by Pivot Architecture, the project’s architects. The virtual community presentation was an extra early-phase community update held by the architects and district to introduce the design team, review the completed community work, and examine the proposed location of the school building, parking lot and playfields. The design team presented the proposed location of site elements, general building shape and project schedule, and invited feedback. Community members were invited to review the presentation and share their thoughts in an online survey.

Camas Ridge Preliminary Design Process Presentation
Presentation Slides
Recorded Video

Camas Ridge Preliminary Site Plan Feedback
www.surveymonkey.com/r/CamasSitePlan (Survey Closed)
Community Feedback on Preliminary Site Plan

Site work and construction will begin in 2022 and the new building will open in 2024.

The new Camas Ridge Elementary School will be designed for safety and security, efficiency and sustainability, and modern teaching and learning. Thanks to the 2018 school bond measure, the new school building will be a high-quality learning environment for students now and for generations to come.

When & Where 

The new building for Camas Ridge will be constructed at its current site. It will be built after Edison Elementary School is completed, with site work beginning in 2022 and the new school opening in 2024.

Camas Ridge cannot continue to operate in its old school building if the new school is to be built in the preferred location on the property, which is smaller than a typical elementary school site and has significant elevation change. The new Edison also cannot be constructed with the school continuing to operate in the old building, as the school property is very small, just 2.6 acres. No other school building in the area has capacity to temporarily house the school programs, so a temporary school site is necessary.

During the 2019–20 school year a temporary school site was prepared at the Willard property (29th & Lincoln) to house first Edison Elementary School from 2020 to 2022 and then Camas Ridge Elementary School from 2022 to 2024, during construction of the new buildings at the existing school sites.

Willard Swing School

Timeline Overview

  • Fall 2018: Bond measure approved by voters Completed
  • Spring 2019: Discussions with staff and parents about next steps Completed
  • Late Spring 2019: Determination of timeline and location for new Camas Ridge and Edison Completed
  • 2019–20: Planning and preparation for school moves Completed
  • 2019–20: Swing school construction at Willard Completed
  • Spring–Winter 2021: New school design development Completed
  • Summer 2022: Camas Ridge moves to temporary school site at Willard In Progress
  • 2022–2024: Construction of new school In Progress
  • 2022–2024: Camas Ridge Elementary School at Willard In Progress
  • Fall 2024: New Camas Ridge Elementary School building opens

About the Project 

• Timeline: Construction begins 2022, new school opens 2024
• Architect team: Pivot Architecture
• General contractor: Chambers Construction
• Capacity: ~450 students
• Existing building history: Constructed in 1949

About the School Bond Measure

In November 2018, voters in Eugene School District 4J resoundingly passed a $319.3 million school bond measure to fund improvements at every 4J school, and replace three aging school buildings with high-quality facilities built for school safety, sustainability, modern seismic standards, and 21st century education. The improvements include new student technology, updated instructional materials, accessibility and equitability enhancements, security upgrades, and building repairs.

Construction Progress (Refreshes every 12 minutes)

OxBlue Construction Cameras

Learn More

Stay informed: Join the 4J bond email list


Nuevo edificio escolar: Primaria Camas Ridge

Los votantes locales aprobaron la medida de bonos escolares en noviembre de 2018 para financiar mejoras de capital en cada escuela de 4J y reemplazar la Primaria Comunitaria Camas Ridge, la Primaria Edison y la Preparatoria North Eugene. Los nuevos edificios escolares serán instalaciones de alta calidad construidas para la seguridad, la eficiencia y la sostenibilidad, los estándares sísmicos modernos y la educación del siglo XXI.

El edificio actual de la Primaria Camas Ridge fue construido en 1949 y se encuentra en malas condiciones.

El nuevo edificio de la escuela se está diseñando ahora; la construcción comenzará en 2022–23 y el nuevo edificio se abrirá en el otoño de 2024. Los estudiantes se mudarán a un sitio escolar temporal por dos años durante la construcción de la nueva escuela.

Actualizaciones del proyecto Camas Ridge 

Celebración de despedida al viejo edificio de Camas Ridge (6.2.22)
Opción de diseño seleccionado para la nueva escuela para Camas Ridge (12.17.21)
Se solicitan comentarios de los diseños para la nueva escuela de Camas Ridge (12.03.21)
Se van terminando los diseños para la Camas Ridge (10.12.21)
Sesión abierta para la participación en el diseño de la escuela Camas Ridge (10.04.21)

Diseño y construcción

El equipo de diseño de Camas Ridge completó el desarrollo del diseño inicial para la nueva Escuela Primaria Camas Ridge en el otoño de 2021. Hay una última oportunidad para dar su opinión sobre las cuatro opciones de diseño desarrolladas por el equipo de diseño.

Aportes sobre el diseño final de la Escuela Primaria Camas Ridge
Encuesta abierta hasta el 12 de diciembre
Aportes recibidos de la comunidad 

El proceso de diseño para el nuevo edificio comenzó con una revisión de la visión desarrollada por la comunidad del distrito, documentos de planificación y materiales de referencia adicionales. El equipo también evaluó la propiedad para identificar oportunidades y consideraciones para el diseño del sitio del nuevo edificio.

El proceso de diseño para cada nuevo edificio escolar individual incluye dos sesiones comunitarias para brindar información y buscar comentarios sobre el diseño esquemático y las etapas de desarrollo del diseño. Se han realizado múltiples reuniones comunitarias adicionales para Camas Ridge. Debido a la pandemia de coronavirus, algunos de estos eventos se han llevado a cabo en línea en lugar de en persona. Los aportes de la comunidad recopilados durante cada fase han ayudado a informar los próximos pasos del diseño escolar.

En marzo de 2021, también se agregó una presentación en línea adicional en la etapa inicial para que la comunidad de Camas Ridge revisase y brindase información sobre el concepto preliminar de ubicación del edificio. Luego, el concepto preliminar del plan del sitio se perfeccionó en respuesta a los comentarios recibidos de la comunidad, incluyendo la reducción del estacionamiento y la reubicación de elementos para proteger un área donde se encuentran una gran cantidad de bulbos de las flores camas.

En cada etapa, los comentarios de la comunidad han informado revisiones y mejoras del diseño de la escuela. A medida que se complete el trabajo de diseño, se considerarán los aportes de la comunidad de la sesión final y el formulario de comentarios para posibles refinamientos del diseño casi final.

Actualización y comentarios sobre el desarrollo del diseño de Camas Ridge: 11 de octubre 
Actualización y comentarios sobre el diseño esquemático de Camas Ridge School: 26 de mayo 
Presentación y comentarios del plano preliminar del sitio de Camas Ridge – 2 de marzo 

El trabajo y la construcción del sitio comenzarán en 2022 y el nuevo edificio se abrirá en 2024.

La nueva Escuela Primaria Camas Ridge estará diseñada para la seguridad, la eficiencia y la sostenibilidad, y la enseñanza y el aprendizaje modernos. Gracias a la medida de bonos escolares del 2018, el nuevo edificio escolar será un entorno de aprendizaje de alta calidad para los estudiantes ahora y para las generaciones venideras.

Cuándo y dónde 

El nuevo edificio de Camas Ridge se construirá en su sitio actual. Se construirá después de que se complete la Escuela Primaria Edison, y el trabajo en el sitio comenzará en 2022 y la nueva escuela abrirá en 2024.

Camas Ridge no puede continuar operando en su antiguo edificio escolar para que la nueva escuela pueda ser construida en su ubicación preferida de su propiedad, que es más pequeña que un sitio típico de una escuela primaria que además tiene un cambio de elevación significativo. La nueva Edison tampoco se puede construir con la escuela funcionando en el edificio antiguo, ya que la propiedad de la escuela es muy pequeña, solo 2.6 acres. Ningún otro edificio escolar en el área tiene capacidad para albergar temporalmente estos programas escolares, por lo que es necesario un sitio escolar temporal.

Durante el año escolar 2019–20, se preparó un sitio escolar temporal en la propiedad de Willard (29th & Lincoln) para albergar primero a la Escuela Primaria Edison del 2020 al 2022 y luego a la Escuela Primaria Camas Ridge del 2022 al 2024, durante la construcción de los nuevos edificios en los planteles escolares existentes.

Sitio temporal escolar Willard (Swing School)

Descripción general del cronograma

  • Otoño de 2018: medida de bonos aprobada por los votantes Completado
  • primavera de 2019: Discusiones con el personal y los padres sobre los próximos pasos Completado
  • fines de la primavera de 2019: Determinación del cronograma y la ubicación de las nuevas Camas Ridge y Edison Completado
  • 2019–20: Planificación y preparación para mudanzas escolares en la Willard Completado
  • Primavera a invierno de 2021: desarrollo del diseño de la nueva escuela Completado
  • Verano de 2022: Camas Ridge se traslada al sitio escolar temporal en Willard En progreso
  • 2022–2024: Construcción de la nueva escuela
  • 2022–2024: Primaria Camas Ridge en el sitio de la Willard
  • Otoño de 2024: Se abre el nuevo edificio de la escuela primaria Camas Ridge

 Acerca del proyecto 

  • Cronograma: La construcción comienza en 2022, la nueva escuela abre en 2024
    • Equipo de arquitectos: Pivot Architecture
    Contratista general: Chambers Construction
    • Capacidad: ~450 estudiantes
    • Historia del edificio existente: Construido en 1949

Acerca de la medida del Bono Escolar

En noviembre del 2018, los votantes del Distrito Escolar de Eugene 4J aprobaron rotundamente una medida de bonos escolares de $319.3 millones para financiar mejoras en cada escuela de 4J y reemplazar tres edificios escolares antiguos con instalaciones de alta calidad construidas para la seguridad escolar, la sostenibilidad y la modernidad. normas sísmicas y educación del siglo XXI. Las mejoras incluyen nueva tecnología para estudiantes, materiales de instrucción actualizados, mejoras de accesibilidad y equidad, actualizaciones de seguridad y reparaciones de edificios.

Obtenga más información