Eugene School District 4J is testing all schools for radon in 2018–19. The district has engaged an independent professional environmental service to conduct the radon testing.
Testing began in November 2018 and will be completed at all district schools over the following months. Results of the tests will be posted on this webpage. Note: As new buildings come online, radon testing will be performed and results posted here.
The Environmental Protection Agency and the Oregon Health Authority recommend that where an initial short-term test indicates a radon level at or above 4.0 picocuries per liter of air (pCi/L), a follow-up measurement using a long-term test should be conducted. If the long-term measurement shows a level of radon above the recommended action level of 4.0 pCi/L, EPA recommends taking corrective measures to reduce radon levels.
School |
Results(click links for detailed lab results) |
Elementary Schools
|
|
Adams Elementary School | No elevated levels |
Awbrey Park Elementary School | No elevated levels |
Buena Vista Spanish Immersion Elementary School | No elevated levels |
Charlemagne French Immersion Elementary School | No elevated levels |
Camas Ridge Elementary School | No elevated levels |
Chávez Elementary School | No elevated levels |
Chávez Elementary School Portables | No elevated levels |
Chinese Immersion Elementary School | No elevated levels |
Corridor Elementary School | No elevated levels |
Edgewood Elementary School | No elevated levels |
Edison Elementary School5 | Initial Testing showed slightly elevated levels in PE Storage Room 191. Follow up testing indicated similar results. Remedial efforts are planned for Spring Break 3/27/23- 3/31/23. Re-testing will follow. |
Family School | No elevated levels |
McCornack Elementary School | No elevated levels |
Gilham Elementary School | No elevated levels |
Holt Elementary School | No elevated levels |
Howard Elementary School1 | Initial testing showed slightly elevated levels in room 138 (community room). Follow up long-term testing confirmed the results. Corrective action was performed and retesting confirmed that the issue is resolved. |
River Road/El Camino del Río Elementary School | No elevated levels |
Spring Creek Elementary School2 | Initial testing showed elevated levels in the staff room. Follow up long-term testing confirmed the results. Corrective action was performed and retesting showed lower levels, but additional corrective action required. Tests conducted after the additional effort confirmed that the issue is resolved. |
Twin Oaks Elementary School | No elevated levels |
Willagillespie Elementary School | No elevated levels |
Willard Swing School, 2855 Lincoln St. | No elevated levels |
Yujin Gakuen Japanese Immersion Elementary School | No elevated levels |
Middle Schools
|
|
Arts & Technology Academy | No elevated levels |
Cal Young Middle School | No elevated levels |
Kelly Middle School | No elevated levels |
Kelly Middle School Portables | No elevated levels |
Kennedy Middle School | No elevated levels |
Madison Middle School | No elevated levels |
Monroe Middle School | No elevated levels |
Roosevelt Middle School | No elevated levels |
Spencer Butte Middle School | No elevated levels |
High Schools
|
|
Churchill High School | No elevated levels |
North Eugene High School3 | Initial testing showed elevated levels in rooms 312 & 600. Follow up long-term testing showed no elevated levels. |
North Eugene High School Softball Building | No elevated levels |
Sheldon High School | No elevated levels |
South Eugene High School | No elevated levels |
Other |
|
4J Transportation Dept. Building | No elevated levels |
4J Facilities Dept. Building | No elevated levels |
4J Ed Center Building4 | Initial testing showed elevated levels in custodial/grounds conference room, custodial equipment repair shop and TSS supervisor office. Follow-up long-term testing confirmed the elevated results only in conference room and repair shop. Corrective action was performed and retesting confirmed that the issue is resolved. |
Bailey Hill Site | No elevated levels |
Building 2120 | No elevated levels |
Coburg Community Charter School | No elevated levels |
Fox Hollow Campus | No elevated levels |
Hilliard House | No elevated levels |
1Howard Elementary School, room 138 (community room): Long-term testing indicated levels at 4.3 and 4.0 pCi/L*, which are slightly above/at the recommended action level of 4.0 pCi/L, requiring follow-up correction and re-testing. As recommended, a concrete slap seal was installed and follow-up short-term testing is scheduled for the 2021–22 school year.
UPDATE (10-28-21): Remediation efforts were successful. No elevated levels of radon were detected in the post-remediation testing.
2Spring Creek Elementary School, staff room: Long-term testing indicated levels at 6.7 and 7.6 pCi/L*, which are above the recommended action level of 4.0 pCi/L, requiring follow-up correction and re-testing. As recommended, a correction on a slab joint was performed and follow-up short-term testing is scheduled for the 2021–22 school year.
UPDATE (10-28-21): Initial remediation reduced radon levels, but follow-up testing showed slightly elevated radon levels at 4.4 and 4.5 pCi/L.* Additional remediation was performed—a couple of small pipe penetrations at the wall heater (inside the wall cavity) were sealed and exhaust fan is programmed to run for two additional hours each day. Follow-up testing is planned.
UPDATE (3-10-22): Additional remediation efforts were successful. No elevated levels of radon were detected in the post-remediation testing.
3North Eugene High School, rooms 312 and 600: Long-term testing indicated levels below the recommended action level of 4.0 pCi/L, thus no follow-up is necessary.
44J Education Center:
– TSS supervisor office: Long-term testing indicated levels below the recommended action level of 4.0 pCi/L, thus no follow-up is necessary.
– Custodial/grounds conference room: Long-term testing indicated levels at 7.9 and 8.2 pCi/L*, which are above the recommended action level of 4.0 pCi/L, requiring follow-up correction and re-testing. Corrective action and follow-up short-term testing are scheduled for the 2021–22 school year. UPDATE (3-10-22): Remediation efforts were successful. No elevated levels of radon were detected in the post-remediation testing.
– Custodial equipment repair shop: Long-term testing indicated levels at 6.0 and 4.3 pCi/L*, which are above the recommended action level of 4.0 pCi/L, requiring follow-up correction and re-testing. Corrective action and follow-up short-term testing are scheduled for the 2021–22 school year. UPDATE (3-10-22): Remediation efforts were successful. No elevated levels of radon were detected in the post-remediation testing.
5 Edison Elementary School, PE Storage and Office room 191: Short-term testing indicated levels of 4.1 pCi/L on 12/5/22 and 4.9 pCi/L on 2/6/23 (average of 2 test samples), which are slightly above the recommended action level of 4.0 pCi/L, requiring follow-up correction and re-testing. Remedial action is scheduled for Spring Break 3/27/23- 3/31/23. Slab penetrations and slab joints will be sealed and re-testing will be scheduled.
*For context, the EPA recommends school officials consider relocating individuals in rooms that have radon levels near 100 pCi/L.