Elementary Schools Construction

Voter Approved Construction Projects
Ellensburg School District is thankful for the community's support in passing our Bond. We know it will have a positive impact on our community and the students we serve. This is why we are so committed to keeping the public informed of all aspects surrounding the Bond. Bookmark this page and be kept up-to-date as we watch our community grow.

This site provides the most up-to-date construction information on Ellensburg School District construction projects. If there is any information you would like to see but cannot find, please email construction@esd401.org.

Quick Updates

2022

January, 2022
  • Lincoln Elementary
    • Selective demo and abatement activities are ongoing
    • Laminated veneer lumber (LVLs) have been installed in the classrooms
    • LVL work at the classrooms for HVAC support is continuing
    • Work to repair the existing damaged second floor joist, which were discovered during construction, is ongoing
    • Interior over framing at the existing walls is being placed
    • Interior framing at classroom and old music room is ongoing
    • Mechanical, electrical, and plumbing work in the new gym is continuing
    • Work on the roof of the new music room is progressing
    • Masonry veneer at the new gym is progressing
February, 2022
  • Lincoln Elementary
    • Demo and abatement activities have completed
    • Interior framing is continuing
    • Door frames are being set as the framing advances and as needed
    • Insulation and vapor barrier is being installed at the exterior walls
    • Drywall and taping is being placed in the gym, music room, and old locker room
    • Mechanical, electrical, and plumbing work in the additions continues and beginning within the existing building
    • The grease interceptor has been set on the north side of the existing gym where the new kitchen is planned
    • Plumbing lines from the kitchen are running under the footing out into the street to connect to the public sewer system
    • Masonry work has concluded at the gym addition and is continuing around the music room addition
    • Masonry for the elevator shaft is nearing completion
    • Fire sprinkler rough-in has started
    • The mezzanine concrete deck over the new kitchen has been placed
    • Rough carpentry at the old gym to infill the floor is mostly complete
    • The framing at the HVAC units is ongoing
March, 2022
  • Mt. Stuart Elementary & Ida Nason Aronica Elementary
    • Landscaping nears completion
    • Staff punch list items are addressed
  • Lincoln Elementary
    • Interior framing activities are moving forward on the first and second floors with focus on the elevator machine room and the kitchen
    • Elevator slab is placed
    • Framing of the kitchen nears completion
    • Soffits are being framed in the old gym and music room
    • The spaces in the old music and locker room has been roughed in and drywall application is ongoing
    • Tape and texture are ongoing in the gym and music room
    • Building wrap, batt insulation and spray foam insulation at exterior walls has been applied at the first floor. Activity will continue to the second floor.
    • Interior painting has been started
    • Flashing at windows is being placed and is being followed up with window frames
    • Canopy construction has started on the south side of the gym
    • Rain leader layout for the canopies is being laid out for tie-in into the roof drain system
    • Civil site work has begun including demolition of the existing fencing
    • Footings and seat walls in the courtyard have been placed
    • Site concrete work and utility pads are being placed
    • Metal siding and flashing at the new gym is being placed
    • Low voltage rough-in on the first floor is ongoing
    • HVAC and plumbing rough-in is ongoing
    • Fire sprinkler installation is ongoing
    • Demo work at the old boiler room is ongoing in preparation for plumbing connection to the deep sewer
    • Window installation is ongoing
    • Wallboard installation within the new gym is underway
  • Early Learning Center (Preschool)
    • Landscaping nears completion
    • Staff punch list items are addressed
April, 2022
  • Mt. Stuart Elementary & Ida Nason Aronica Elementary
    • Landscaping completed with the exception of hydroseed, which will be by the end of the month
  • Lincoln Elementary
    • Interior framing activities are ongoing and focused in the old cafeteria area and first floor restrooms
    • Framing at the elevator has finished
    • Sheetrock activities have moved to the second floor
    • Chimney demolition completed
    • Acoustical panels are being installed in the new gym
    • Riser room sprinkler connection has been completed
    • Sprinkler rough-in is continuing
    • Most of the metal door frames have been set
    • Windowsills and window flashing are being installed
    • Most of the window frames have been set, glazing is being installed
    • Roof parapet work is continuing
    • Siding and flashing work are ongoing in the old cafeteria
    • Low voltage work has begun
    • Electrical rough-in in the classrooms is nearing completion
    • Painting at the new canopies outside the new commons and gym are complete
    • Painting of the classroom interiors is being done as they become available
    • Elevator is installed
    • Concrete sidewalks and seat decks are being installed
    • Underground utilities, plumbing, sewer, and rain leaders are being installed
    • Grease interceptor is being set
    • HVAC and plumbing rough-in is ongoing
    • Wallboard installation within the new gym is completed and painted
  • Early Learning Center (Preschool)
    • Landscaping completed with the exception of hydroseed, which will be by the end of the month
May, 2022
  • Lincoln Elementary
    • Flat concrete work at the streets is complete
    • Asphalt pave back is complete
    • Chimney has been removed
    • The mechanical pads for the HVAC units in the mechanical room have been placed
    • Interior framing is continuing. Work is focused around the area of the old boiler room.
    • Sheetrock activities are following the framing work as areas become available
    • Ceiling grid is being placed on the second floor and in the music room
    • Ceiling and acoustical panels are onsite
    • Rough carpentry is ongoing
    • Library windows have been installed
    • Window frames have been installed. Glazing is being installed.
    • Painting continues throughout as rooms become available
    • Doors are being installed
    • Existing hardwood floors are being refinished along the sink wall and prepared for new carpet flooring finish throughout the rest of the classroom areas
    • Casework is being installed as rooms become available
    • Electrical rough-in is ongoing
    • Plumbing and HVAC work is continuing
    • Boiler pads have been installed. DOES unit is scheduled for installation.
    • Fire sprinkler work is complete
    • Exterior caulking and weather protection is continuing
    • Siding at the elevator is being installed
    • Site work utilities are completed
    • Playground concrete curb placement is completed
    • The pathway around the playground is being located and rough grading/base is being placed for asphalt paving
    • Irrigation system is being laid out for subgrade installation
June, 2022
  • Lincoln Elementary
    • Interior framing is ongoing
    • Sheetrock activities are ongoing. This activity is ongoing throughout the structure as the areas become available.
    • Acoustical Tile activities are continuing. Most of the work is contained to the second floor.
    • Electrical rough-in is continuing
    • Mechanical and plumbing rough-in is continuing in the restrooms
    • Painting activities are ongoing throughout the classrooms
    • Brick sealer will be applied to the new gym when weather is cooperative
    • Window glazing is being set in the new library
    • First floor casework is ongoing. Second floor casework is to be delivered this month.
    • Carpet is being installed at the first floor classrooms
    • Landscaping is continuing
    • The last portable has been removed
July, 2022
  • Lincoln Elementary
    • Sheetrock activities are ongoing. Additional help has joined and activity is ongoing throughout the structure.
    • Ceiling tile are being installed
    • Acoustical panels are being installed in the new commons
    • FRP at the restrooms is being applied
    • Electrical and data room work is continuing
    • Hydronics and plumbing for HVAC is ongoing. Most of the work is confined to the crawl spaces and mechanical room.
    • Mini split systems are being installed
    • Fire sprinkler work is progressing to pick up the mandated Fire Marshal's changes
    • Wood base in the classrooms is being refurbished
    • Wood door frames have been delivered and will be installed as areas become available
    • Painting activities are ongoing. Most of the painting activities are confined to the first floor restrooms and touching up the new gym and commons.
    • Window and door hardware is being installed
    • Casework is being installed as spaces become available
    • Flooring at the kitchen has been placed
    • Site utilities at the new parking lot are being placed. Swale surfaces and concrete curbs for the parking lot are being prepped.
    • Landscaping at the new parking lot is being planted
    • Site fencing will be installed upon completion of planting
    • Transformer is scheduled to be placed by the City
    • Parking lot lights and hanging light fixtures are being placed in preparation for permanent power
    • Asphalt for the new parking lot is scheduled for early August with striping to follow shortly after

Parents, Staff, Students and Community Members,

The Ellensburg School District Board of Directors authorized a bond proposition to be placed on the November 6, 2018, special election ballot to alleviate overcrowding and address critical safety and maintenance concerns at the elementary school level. This plan will add space, build a replacement Mt. Stuart Elementary,  and renovate Lincoln Elementary, and build a new elementary school on newly purchased property on the northwest side of town.

Resolution 06.10.18

Essential facts about the 2018 bond
Cost & tax rate estimates