Fairport Central School District

Fairport High School Logo Small1

Work on the 2019 voter-approved Fairport Forward Capital Improvement Project is well underway at Fairport High School (FHS). During the week of June 28, crews with Campus Construction and Labella Associates began removing kitchen equipment and moving it to the gymnasium for temporary storage. As the construction part of Phase 1A of the project began and ceiling panels were removed, crews covered lockers in the hallways adjacent to the cafeteria. Meanwhile, crews monitored a family of ducks that had made its home in the cafeteria courtyard. After the last egg hatched on June 30, Perinton Animal Control safely relocated the family! 

Construction crews say the abatement process and demolition are expected to begin on the second story science classrooms later this month. You can find more information on the capital project plan and progress here.

Duck Photo #1

Cafeteria Corridor South Of Cafeteria Corridor West Of Cafeteria Existing Kitchen Equipment Kitchen #1