Next Generation Colonie – 2025 Facilities Improvement Capital Project

logo for capital project

On Oct. 18, voters in the South Colonie Central School District approved two capital project propositions that together will result in more than $120 million in improvements across the district.

Proposition #1

Proposition #1 includes a $112.5 million dollar capital project referendum to address aging infrastructure, improve instructional spaces, and provide essential safety upgrades districtwide. Project to include instructional space enhancements including auditoriums and athletics, a new transportation facility, and district office expansion to meet current operating needs.
Yes – 1151 / No – 408  (74% in favor)

Proposition #2

Proposition 2 includes a $7.5 million dollar debt neutral proposition for the South Colonie to receive an additional 10% building aid on an energy performance contract (EPC) to improve energy efficiencies in all buildings. The cost of the EPC is offset in energy saving costs and would have no additional tax impact to residents.
Yes – 1234/ No –  323  (79% in favor)

Updates will appear on this page as the development of the capital project planning moves forward.

Project Updates Updates
Building History
Construction Stage Timeline 
Proposed Project Timeline
Project Videos 
Board Presentations
FAQs


Updates

The latest full update can be found here. 


Next Generation Planning


Building history

Colonie Central High School 

  • 1952, built
  • 1989, MUG gym addition
  • 2000, New math wing  added (10 classes)

Sand Creek Middle School 

  • 1968, built
  • 2000, new classrooms/gold gym

Lisha Kill Middle School

  • 1958, built
  • 2000, New classrooms
  • 2006, New tech rooms

Roessleville Elementary

  • 1972, built
  • 2018, new library

Forest Park Elementary

  • 1966, built
  • 2000, new classrooms
  • 2018 new library

Shaker Road Elementary

  • 1958, built
  • 2000, new classrooms
  • 2006, new library

Saddlewood Elementary

  • 1958, built
  • 2000, new classrooms
  • 2006, new library

Veeder Elementary

  • 1966, built
  • 2000, new classrooms
  • 2006, cafeteria expansion, new small gym

Bus Garage

  • 1948, built
  • 1957, added bus barn
  • 1991,  added office area and driver room updates
  • 1998, built a two bay garage building in 1998 after NYSDOT deemed current
    garage unsafe

District Office

  • 1971, built (intended to be a temporary 20 year location)

Construction Stage Timeline 

Work will occur in three stages with planning and design occurring simultaneously. 

Stage I

Graphic showing stage 1 timeline
Stage I: Site, Athletics, and Academic Building Upgrades
Black and white rendering of elementary pilot classroom
Black and white rendering of elementary pilot classroom

Board of Education members and district leadership have been working collaboratively to engage stakeholders on the first stage designs. The design work for stage 1 of the project is set to be submitted to the New York State Education Department (NYSED) for approval by Fall 2023.

Project highlights for Stage 1 include:

Elementary classrooms

      • SEI design group in conjunction with South Colonie leadership has been creating a model elementary classroom of the future. The classroom will be piloted at Shaker Road Elementary in the first design submissions to state ed.
      • Two stakeholder meetings have been held on January 26 and May 25.

High School Athletics and PE Spaces

      • Spaces include the field entrance building, Turf field complex, fitness center, and athletic office,
        Fitness Center rendering
        CCHS Fitness Center

        Mug boys team/locker rooms, MUG girls team/locker rooms, basement boys and girls team rooms, PIT locker rooms, and athletic trainer’s suite.
      • Two stakeholder meetings have been held Feb. 9 and June 1.

High School Classrooms

      • SEI design group in conjunction with South Colonie leadership has been working to create a modern classroom environment for high school students.
      • One stakeholder meeting has been held on Feb. 7. Building utilization study was conducted on May 25. Further discussion for special education with full committee follow-up are planned.

Shaker Road Bus Loop

      • SEI design group in conjunction with South Colonie leadership has been working to create a bus loop design that will improve safety and reduce the impact on local neighborhoods.
      • One stakeholder meeting has been held on Jan. 26 with a follow-up meeting being planned.

Lisha Kill Facade

      • SEI design group in conjunction with South Colonie leadership has been working to create a modern facade with priorities of safety and energy efficiency.
      • Two meetings were held regarding the planning. One on January 17 and a final meeting held on May 24.

Auditoriums

      • SEI design group in conjunction with South Colonie leadership has been working to create safe, functional, and aesthetically pleasing auditorium spaces for CCHS, Lisha Kill, and Sand Creek Middle Schools.
      •  One stakeholder meeting was held on Feb. 7 with a follow-up meeting held on May 16.

Nurses Suites

      • SEI design group in conjunction with South Colonie leadership has been working to create safe, functional, and aesthetically pleasing nurses suites for all elementary and middle schools.
      • One stakeholder meeting was held on Feb. 2 with a second meeting being planned.

The design process and stakeholder input meetings are proceeding as planned across the board.


Stage II: 

Project timeline for stage 2

Stage II: Veeder Library and Academic Building Upgrades

Stage III: 

Graph out planning timeline for Stage 3
Stage III: Transportation Center and District Office Expansion

 

 

 

 


Project Overview

 At this time, the district has identified $112.5 million in infrastructure projects that will provide improvements at every school building in the district. The priority projects include: 

Colonie Central High School

    • Auditorium renovations – Front of house improvements
    • Library Media Center renovations – ARPA federal funds
    • Classroom renovations (290’s, 110’s, 210’s)
    • Locker room renovations 
    • Restroom renovations
    • Upgraded fitness center
    • Replace fire alarm system with combined FA/PA
Two images side by side one showing current outdated high school classroom and the other showing updated classroom space.
Current classroom at Colonie Central High School and sample mockup of updated high school classroom.

Lisha Kill Middle School

    • Site roadway enhancements – Drop off lane and front sidewalk reconstruction
    • Resurface outdoor playcourts and provide new backboards
    • Auditorium renovation
    • Locker room and team room enhancements
    • New exterior walls/facade on the original portion of the building
    • Upgraded nurses’ office suite and restrooms near the auditorium
    • Restroom renovations
    • Classroom renovations
    • Internal cosmetic changes (upgrades to the wood paneling)
    • Replace fire alarm system with combined FA/PA
Pictures showing horrible front facade of a school and two images of upgraded areas including a classroom and auditorium area.
Front facade of Lisha Kill that needs to be replaced. Sample updated classroom and updated Auditorium.

Sand Creek Middle School

    • Auditorium renovation
    • Classroom renovations
    • Locker rooms and adjacent bathrooms enhancements
    • Fitness center enhancements
    • Music area enhancements
    • Restroom renovations
    • Updated nurses’ office suite
    • Replace fire alarm system with combined FA/PA
Current and updated classroom sample. Sample of new instructional group space and upgraded auditorium at Sand Creek Middle School.
Current and updated classroom sample. Sample of new instructional group space and upgraded auditorium at Sand Creek Middle School.

Athletics

    • Synthetic turf multi-use athletic field (Ambrosio stadium field) Field Complex with concession upgrades and bathroom facilities
    • High school fitness center upgrades
    • New Team Rooms
    • Refinish MUG Gymnasium Wood Floor
four images one imaging showing current team room and three others showing upgrades to the athletic facilities including turf field and new gym area
Current and upgraded team space at Colonie Central High School. New synthetic turf field complex including bathrooms and upgraded fitness center at CCHS.

Transportation, Buildings & Grounds, District

  • Transportation, O&M facility to support a fleet of 75 buses and 150 employees
  • Enhancements and expansion to South Colonie District Offices to meet current needs

four images showing current transportation facility and limited work space and then a mock digital drawing showing more modern open workspace and front facade
Current transportation facility and work space and then mockup of front façade and indoor space at new transportation facility.
Former Capital Region BOCES site and home of proposed New South Colonie Transportation and O&M Facility. Image shows mockup of site design.
Former Capital Region BOCES site and home of proposed New South Colonie Transportation and O&M Facility. Image shows mockup of site design.

Elementary Schools

    • Playground improvements at all elementary schools 
    • NEW Library Media Center at Veeder Elementary
    • Classroom renovations
    • Nurses office remodels
    • Restroom renovations/upgrades 
    • New bus loop at Shaker Road
    • Window and HVAC upgrades as needed

Two pictures side by side showing Current library space at Veeder Elementary and sample mockup of new library and media center.
Current library space at Veeder Elementary and sample mockup of new library and media center.
Current elementary and updated elementary classrooms
Current elementary and updated elementary classrooms
two pictures showing nurses area
Current and mockup of updated Nurses’ Suite

Technology

    • Additional security cameras districtwide
    • Secure card access entry points at all buildings
    • Technology infrastructure upgrades

Other

    • Roofing Replacements at CCHS, Roessleville, Shaker Road, Sand Creek, Veeder, Forest Park and Saddlewood
    • HVAC improvements at CCHS, Shaker Road, Sand Creek, Veeder, Lisha Kill, Forest Park, Saddlewood and Roessleville
A picture of the current roof at Sand Creek Middle School. Shows a horrible condition roof.
Current roof at Sand Creek Middle School

The majority of the projects were part of the district’s five-year capital facilities plan. The plan prioritizes infrastructure needs by building and provides a blueprint for the district to develop moderate-sized capital projects approximately every 3-5 years. The most recent capital project was approved by voters in October 2016 and will be completed in the summer 2022.


Project Videos

Next Generation Colonie 2025

New Transportation Facility to support growing fleet of buses