  • On this page you will find information regarding the ongoing progress and events related to the construction taking place near the Administration Building.

    April 16th to 20th

    • Rough grading of bus parking will continue
    • Pond grading will begin
    • Heavy traffic on site, including tracked equipment and trucks

     

    April 9th to 13th

    • Site demolition will be completed and spoils will be removed from site
    • Rough grading of bus parking area will begin:
      • Topsoil will be stripped and stockpiled
      • Excavation and relocating of material from bus parking area to pond area
    • Heavy traffic on site, including tracked equipment and trucks

    April 2nd to April 6th

    • NLI will continue to work with all parties to obtain approved plans and associated permits from the City of Marble Falls.
    • Installation of final erosion control measures
    • Site demolition will continue, including concrete and asphalt paved areas.
    • Heavy traffic on site, including tracked equipment and trucks

    March 19th to March 23rd

    • Erosion Control Installation
    • Complete Canopy Demolition
    • Building Demolition (limited)