Please Pardon Our Mess ...
-
On this page you will find information regarding the ongoing progress and events related to the construction taking place near the Administration Building.
April 16th to 20th
- Rough grading of bus parking will continue
- Pond grading will begin
- Heavy traffic on site, including tracked equipment and trucks
April 9th to 13th
- Site demolition will be completed and spoils will be removed from site
- Rough grading of bus parking area will begin:
- Topsoil will be stripped and stockpiled
- Excavation and relocating of material from bus parking area to pond area
- Heavy traffic on site, including tracked equipment and trucks
April 2nd to April 6th
- NLI will continue to work with all parties to obtain approved plans and associated permits from the City of Marble Falls.
- Installation of final erosion control measures
- Site demolition will continue, including concrete and asphalt paved areas.
- Heavy traffic on site, including tracked equipment and trucks
March 19th to March 23rd
- Erosion Control Installation
- Complete Canopy Demolition
- Building Demolition (limited)
Please stay clear of the area. This is a phase of the project that creates hazardous conditions at the construction site, and the company will clear the material from the site as quickly as possible.