| Phases |
Facility |
Project Description |
| 1. Planning |
PGES |
School Wide: HVAC Replacement |
| 2. Design |
CES |
Bldgs. 1, 4, 5 & 6: Bldg Env Repairs w/Cafe Walkway Drainage |
| 2. Design |
EES |
Bldg 4 Roof Replacement |
| 2. Design |
Fac Ops |
HVAC |
| 2. Design |
HHS |
Theater Renovation |
| 2. Design |
Transportation |
(2) EHPA Generators |
| 2. Design |
WHMS |
Bldg. 7: LED & Emergency Lighting / Ceilings |
| 2. Design |
Endeavor |
Roof Replacement |
| 2. Design |
SHS |
Theater Renovation |
| 2. Design |
CES |
Roof Replacement |
| 4. Construction |
CHS |
Exterior Lighting |
| 4. Construction |
NCTHS |
Bldgs. 1, 2 & 7: Building Envelope Repairs |
| 4. Construction |
WES |
Canopy & Lighting |
| 4. Construction |
HHS |
School Wide: HVAC Replacement |
| 4. Construction |
HHS |
Fire Alarm Replacement |
| 4. Construction |
SHS |
Athletic Field Lighting Replacement |
| 4. Construction |
WES |
Emer. & Exit Lighting Replacement |
| 4. Construction |
County Wide |
FEMA generator replace nuts, bolts and paint |
| 5. Close Out |
FCMS |
Multiple Buildings: Roof Replacement |
| 5. Close Out |
PGES |
HVAC Chilled Water Piping Replacement |
| 6. Warranty |
HHS |
Intercom System Replacement |
| 6. Warranty |
WHMS |
School Wide: Egress Window Replacement |
| 6. Warranty |
FacOps |
Thermal Insulation Replacement (Phase 1) |
| 6. Warranty |
HHS |
Bldg. 24: Roof Replacement |
| 6. Warranty |
JDFES |
School Wide: HVAC Replacement |
| 6. Warranty |
Multiple Sites |
Gym Floor Repair/Resurfacing (5 HS, 2 MS) |
| 6. Warranty |
PGES |
School Wide: Roof Replacement |
| 6. Warranty |
WHMS |
Gym Floor and Bleacher Replacement |
| 7. Complete |
CHS |
Upgrade Fire alarm system |
| 7. Complete |
County Wide |
Fencing |
| 7. Complete |
County Wide |
County wide flooring |
| 7. Complete |
County Wide |
Intercom upgrades/Fire Alarm |
| 7. Complete |
DSPMS |
Gym Bldg. New Electrical Room (in Classroom) |
| 7. Complete |
HHS |
Replace PA System |
| 7. Complete |
HHS |
Press Box |
| 7. Complete |
HHS |
Construct ADA compliant restrooms/baseball |
| 7. Complete |
SHS |
Replace fire alarm system |
| 7. Complete |
SHS |
Gym floor and bleachers |
| 7. Complete |
SHS |
Track replacement |
| 7. Complete |
WHMS |
Phase 2 HVAC Upgrades |
| On-Going |
County Wide |
County Wide Project - Maintenance |