Build new gymnasiums, relocate covered play spaces, resurface tracks, resurface tennis courts, fix pool decking and mechanical systems.
- The Centennial Middle School Track has been completed and reopened; the Oliver Track is expected to be completed in early Fall of 2021.
- The four Gymnasium additions are all scheduled to be completed between Fall of 2021 to early Fall of 2022.
- Centennial High School pool and locker room repairs, and Tennis Court Relocation are all scheduled to be completed in Fall of 2021.