Bond Construction Schedule

Logo 

Updates From The 2011 School Bond

  

Project Begin Construction  Completion 
Stadium Parking Renovations February 2012 July 2012
South Houston Elementary
New Addition and Renovations 
July 2012 July 2013
Queens Intermediate
Replacement School 
September 2012  March 2014 
Veterans Memorial Sports Complex
Additions and Renovations 
November 2012  September 2013 
Rayburn High School and South Houston High School
New Competition Gymnasiums 
December 2012  September 2013 
Tegeler High School
New Pod Addition 
December 2012  June 2013 
Career Technical Education High School
New School 
December 2012  June 2014 
Keller Middle School
Replacement School 
February 2013  June 2014
Facility Assessment A
Renovations at 18 Schools 
March 2013  August 2013 
Facility Assessments B
Renovations at 25 Schools 
March 2013  August 2013 
South Shaver Elementary
Replacement School 
April 2013  June 2014 
Gardens Elementary
Replacement School 
May 2013  June 2014 
Middle School #11
New School 
October 2013  February 2015 
Parkview Middle School 
New School 
October 2013  February 2015 
Queens Middle School
New School 
April 2014 August 2015 
Six Middle School Gymnasiums
New Gymnasium Additions 
September 2014  July 2015