01/24/25 | Marshall Elementary Construction Update

January 24, 2025
Progress on the new Marshall Elementary School is in full swing, with exciting milestones reached over the past two months. Construction Superintendent David Heckard and Flagstaff Unified School District’s Director of Operations, Justin Nabors, recently shared updates on the project’s advancements as crews work steadily through winter conditions.
At the north entrance of the school, construction on what is being called the “canyon” corridor is taking shape. This continuous hallway stretches from the north to the south end of the building, featuring high masonry walls and exposed sealed wood ceilings that will create a modern and open space. In the gymnasium, crews have completed pouring the slab-on-grade, along with the stage and ADA-accessible ramp, ensuring these key elements were in place before winter weather set in.
On the east side of Area B, significant progress has been made with the installation of roof sheathing over glulam beams, trusses, and steel structures. With this foundational work complete, roofers are set to begin installing the final roofing in January. The design of Area B also incorporates a raked roofline with large south-facing windows that will allow ample natural light to illuminate the classrooms, creating an inviting learning environment for students.
Beyond the building itself, plans for the outdoor spaces are also coming together. The south side of the school will feature a playground area with a basketball court, four-square boxes, and a spacious grass playfield for students to enjoy. Meanwhile, crews are working diligently to install underground utilities, including APS primary lines and an eight-inch waterline, which will connect to the school’s mechanical room. Interior construction is progressing as well, with teams working on mechanical, electrical, plumbing, and fire sprinkler systems. Interior block insulation and framing began in mid-January, signaling another phase of development.
As the project moves forward, cranes are currently on-site finalizing roof installation while construction teams continue enclosing the building. Work on utilities and interior systems will extend into February, keeping the project on track to provide Marshall Elementary School students with a state-of-the-art learning environment.
Stay tuned for more updates as we get closer to the completion of this exciting project.